Create and Edit a Build Plan Budget

Modified on Wed, Jul 29 at 10:36 AM

TABLE OF CONTENTS


Create and Edit a Build Plan Budget

This article walks through the Budget workflow on a Build Plan: open the Budget card, enter lines and planned revenue, save, submit for approval, delete a pending revision, or revise an approved budget.


For setup (Budget Items, Templates, Scenario links) and access rights, see Build Plan Budgets. For approver steps, see Build Plan Budget Approval.





Before you start

You need:

  • Financial employee role and financial access to the Build Plan
  • Pending revision to edit (or an Approved revision to Revise)
  • Budget Items and Templates set up if you plan to use FILL FROM TEMPLATE





Open the Budget

From the Build Plan

  1. Open the Build Plan card or select it on a dashboard.
  2. Go to the Budget tab.
  3. Click Open Budget, or open a revision from the Revisions sub-tab.




Automatic first Budget

When a Project Scenario links to a Budget Template and you generate a Build Plan from that scenario, Fieldclix may already create revision 1 in Pending status with lines from the template.




Manual first Budget

If no Budget exists:

  1. Open the Build Plan Budget tab.
  2. Click Create to create revision 1 in Pending status.
  3. Add lines and planned revenue (steps below).






Budget card layout

The Budget card has three tabs:

TabUse
GeneralHeader, financial summary, budget lines, main actions
DocumentsAttach supporting files
Approval ProcessApproval route status (when submitted)




Header fields

FieldMeaning
Build PlanLinked Build Plan
RevRevision number
StatusPending, Approved, or Obsolete
Overhead TypeOverhead category (Change while Pending)
Created / Submitted / Approved / EffectiveLifecycle dates
DescriptionPurpose of this revision (Change while Pending)




Summary row

MetricMeaning
Sales Order AmountTotal from linked Sales Orders (when used)
Planned RevenueRevenue you plan to earn
COGSPlanned cost of goods sold (direct + pass-through)
Gross Profit MarginPlanned revenue minus direct COGS ($ and %)
OverheadOverhead allowance from Overhead Type ($ and %)
Profit MarginGross profit minus overhead ($ and %)


After line or revenue changes, click RECALCULATE TOTALS if the summary does not refresh.



Configurable (your instance)
When Disable Pass Through is on, margins use Total Revenue only; Service Revenue is not split out. See Pass Through Setting.





Edit budget lines

Only Pending revisions can be edited.

  1. On the General tab, click EDIT LINES.
  2. Add, change, or remove rows.
  3. Click SAVE LINES (or CANCEL to discard).




Line columns

ColumnMeaning
Budget ItemFrom catalog or line name
TypeLabor or Non-Labor
QTY/AmountHours (Labor) or dollar amount (Non-Labor)
Cost RateHourly rate for Labor
TotalCalculated line total
Financial AccountAccount for this line
Service ItemOptional reporting breakdown
VendorOptional reporting breakdown 
CommentsLine notes





Line actions

ActionWhat it does
+ ADD ROWInsert an empty line
FILL FROM TEMPLATEAdds lines from a Budget Template
Row delete iconRemove one line



Configurable (your instance)
Service Item enables [SI] sub-rows on the Build Plan Budget tab (for example Field Labor[SI] Electrical). Unassigned costs show as <Unassigned Service Item>.

Configurable (your instance)
Vendor enables [V] sub-rows (for example [V] Talley under Material Expenses).

Configurable (your instance)
Use a pass-through Financial Account (for example Pass Thru Materials) when the cost should be client-reimbursable in budget and P&L.






Set planned revenue

Planned Revenue is what you expect to bill on the Build Plan.


While the Budget is Pending:

  1. Click Change next to Planned Revenue on the summary, or
  2. Click FILL FROM SALES ORDERS to pull the total from linked Sales Orders.

Compare Sales Order Amount on the summary with Planned Revenue when both are used.





Submit for approval

When the Budget is complete:

  1. Review the summary and lines.
  2. Click RECALCULATE TOTALS if needed.
  3. Submit the Budget for approval — click Send for approval.


Fieldclix creates an inbox job for the configured approver.

What happens nextDetail
Status stays Pending until approvedYou can still edit if not yet submitted, or after For revision
Auto-approvalIf rules allow (submitter is approver, or role has no approval required), Fieldclix approves immediately
Approver inboxApprover completes the job—see Build Plan Budget Approval


Configurable (your instance)
Financial + Advanced Budget Manager can click APPROVE on the card to approve without completing the inbox job.


Even when auto-approval applies, you still initiate the approval step.






Delete a pending budget

Remove a Budget only while it is Pending:

  1. Open the pending Budget card.
  2. Click DELETE.
  3. Confirm.

You cannot delete Approved or Obsolete revisions.





Revise an approved budget

You cannot edit an Approved Budget in place.

  1. Open the Approved Budget card.
  2. Click Revise.
  3. Fieldclix creates a new Pending revision (next Rev number) with copied lines.
  4. Edit lines, revenue, Overhead Type, or description.
  5. Submit the new revision for approval.

When the new revision is Approved, the previous one becomes Obsolete.






Budget Effective Date

The Effective Date decides which approved revision applies for WIP and financial reporting on a given date.

SituationHow it is set
DefaultApproved date at approval
First revision on a started Build PlanOften Build Plan Started date
Manual changeAccountants and Bookkeepers can adjust after approval


Changing Effective Date affects WIP and adjusted P&L—not only the Budget card.





Quick reference — actions on the Budget card

ActionWhen availableWho
EDIT LINES / SAVE LINESPendingFinancial (BP access)
Change Planned Revenue / Overhead / DescriptionPendingFinancial
FILL FROM SALES ORDERSPendingFinancial
RECALCULATE TOTALSPendingFinancial
SEND FOR APPROVALPendingFinancial
APPROVEPending (under approval)Financial + Advanced Budget Manager
DELETEPendingFinancial
REVISEApprovedFinancial
SHOW APPROVERSAnyUsers with access to the budget






Related articles







Q&A

Q: Why is my Budget empty after I open it?
A: No template was applied at generation and no lines were added. Use FILL FROM TEMPLATE, + ADD ROW, or ask your administrator to link a template to the Project Scenario.


Q: Can I edit an approved Budget?
A: No. Use Revise to create a new Pending revision.


Q: Can I delete an approved Budget?
A: No. Only Pending revisions can be deleted.


Q: Who can delete a pending Budget?
A: Users with Financial access to the Build Plan.


Q: What if I submit and need to change lines?
A: If the approver returns it For revision, edit and resubmit. If still Pending before anyone acts, your process may allow further edits—check with your administrator.


Q: When should I use Service Item on a line?
A: When you want expense breakdown below the financial account on the Build Plan Budget tab and in reports—for example Electrical and Concrete under Field Labor.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article